    LA Metro subway extension pushed back to fall 2027

    November 23, 2026 at 7:27 pm
    Rendering of an Amtrak Airo trainset traveling among green vegetation. (Amtrak)

    Amtrak orders longer Airo trains for busy Northeast Corridor

    November 23, 2026
    Rendering shows the proposed California High-Speed Rail bullet train traversing through the California Central Valley. (California High-Speed Rail Authority)

    California High-Speed Rail consultants return $1 million spent on restaurants, travel

    November 20, 2026
    Facebook Instagram Threads Bluesky X (Twitter) LinkedIn YouTube
    Rail and Runway
    • Airlines
    • Transit
    • Cruises
    • R & R
      • Hotels
      • Theme Parks
      • Festivals
      • Entertainment
      • Travel Guides
      • More News
    Facebook Instagram Threads Bluesky X (Twitter) LinkedIn YouTube
    Rail and Runway
    Home»Transit»LA Metro subway extension pushed back to fall 2027
    A subway train at the platform of the new D Line station at Wilshire and La Cienega show in this undated promotional image from LA Metro.
    A subway train at the platform of the new D Line station at Wilshire and La Cienega show in this undated promotional image from LA Metro.
    Transit

    LA Metro subway extension pushed back to fall 2027

    Travis SchleppBy Travis SchleppNovember 23, 2026 at 7:27 pm6 Mins Read

    The LA Metro subway extension into West Los Angeles is being pushed back several months, to fall 2027.

    Last week, LA Metro officials revealed that Section 2 of the D Line extension, which will serve Beverly Hills and Century City, is being pushed back from late spring 2027 to fall 2027, most likely in September.

    Details of the LA Metro subway extension delay were first published in a presentation to the LA Metro Board Finance Committee.

    The report states that, despite being 95% complete as of September 2026, Section 2 will need a few more months than originally planned before it can open to the public.

    A train at the new D Line station at Wilshire/La Cienega, part of the LA Metro subway extension, in an undated promotional image from LA Metro.
    A subway train at the platform of the new D Line station at Wilshire and La Cienega show in this undated promotional image from LA Metro.

    As Joe Linton of Streetsblog LA reports, Section 2 of the D Line extension has seen a $300 million budget increase due to unforeseen obstacles that weren’t in the previous budget.

    “Among them are tunneling around old oil wells (under Beverly Hills High School), upgrading tunnel seismic lining to be stronger than initial planned, realigning Century City station (also to avoid old oil wells), realigning a Century City storm drain (to avoid ventilation impacting a mall), compliance with construction restrictions imposed by Beverly Hills, and more,” Linton writes.

    Those unexpected obstacles have led to the longer timeline and pushed the budget to a new total of $2.87 billion.

    But Metro’s chief program management officer Tim Lindholm said this would be the final budget increase and that the additional funding would ultimately get the project over the finish line.

    The cost increase for the LA Metro subway extension still needs final approval from the full Metro board, which will vote on it next month.

    Read More: World Cup, Pride events deliver ridership numbers for LA Metro

    The delay puts the opening of the LA Metro subway extension’s Section 2 within a few months of Section 3, which is now scheduled to open in December 2027. Section 3 is about 90% complete and work on both sections continues simultaneously, so the delay shouldn’t have a major impact on either project.

    LA Metro subway extension already a hit

    Section 1 of the D Line extension was completed earlier this year and opened to the public on May 8, 2026. The 3.92-mile extension introduced new stations at Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienega, and was an overnight, massive success for LA Metro ridership.

    LA Metro says D Line ridership nearly doubled year over year in September, including 114% growth on weekdays. Overall, D Line ridership grew by 93%, while the next-highest increase on LA Metro rail was on the E Line, at about 10%.

    Read More: LA Metro project in crucial traffic corridor gets boost by federal government

    Ridership numbers will likely climb even higher when the LA Metro subway extension continues west next year.

    Section 2 will extend the D Line into Beverly Hills at Beverly Drive and into Century City, while Section 3 will add two stops in Westwood at UCLA and the VA Hospital.

    A public art display at the Wilshire/Fairfax Station along the LA Metro D Line shown in this undated image from LA Metro.
    A public art display at the Wilshire/Fairfax Station along the LA Metro D Line shown in this undated image from LA Metro.

    When fully built out, the D Line Subway Extension Project will add about nine miles of underground track and seven new stations, including the three that opened in May, along its route from downtown Los Angeles to the Westside.

    More LA Metro projects in the works

    In addition to the D Line extension, several other long-awaited transit projects are in the works for LA Metro.

    The East San Fernando Valley light rail line held a groundbreaking ceremony earlier this month. The 6.7-mile line will bring 11 new stations along the Van Nuys Boulevard corridor and connect Van Nuys with Pacoima. The project was originally planned to be operational by 2027 but has since been pushed back to 2032.

    Read More: Nithya Raman unveils plans for late night LA Metro train service

    Days after that groundbreaking, Metro broke ground on the Vermont Bus Rapid Transit Line, a 12.4-mile bus line with dedicated lanes that connects Sunset Boulevard in East Hollywood to 120th Street in the Athens neighborhood of South Los Angeles. LA Metro hopes to have it completed in time for the 2028 Olympics.

    A map from LA Metro shows the proposed route of the Vermont Bus Rapid Transit Line connecting East Hollywood to Athens in South L.A. (LA Metro)
    A map from LA Metro shows the proposed route of the Vermont Bus Rapid Transit Line connecting East Hollywood to Athens in South L.A. (LA Metro)

    LA Metro is building another bus rapid transit line to connect cities and neighborhoods in northeast L.A., with a goal of having it done by 2028, despite opposition from some neighborhood groups and city councils. The North Hollywood to Pasadena Bus Rapid Transit system would connect North Hollywood in the west with Pasadena in the east, with stops in Burbank, Glendale and Eagle Rock along the way.

    Like the Vermont line, the North Hollywood to Pasadena line would use zero-emission buses traveling mostly in dedicated bus lanes, although buses would have to merge into mixed-flow traffic in several spots along the route.

    Construction on the A Line extension into Claremont is also expected to begin by late 2027 or early 2028. The longest light rail line in the world expanded into Pomona just last year, but where it will finally stop remains to be seen, as original plans to extend all the way to Montclair in San Bernardino County have been put on hold.

    In the coming decades, LA Metro will begin work on several major projects: the 14.5-mile Southeast Gateway Line, which will give the Gateway Cities region its own light rail line; a third subway line connecting the San Fernando Valley to the L.A. Basin via the Sepulveda Pass; and an extension of the K Line to Torrance in the south and the Hollywood Bowl in the north.

    The first two are tentatively scheduled to be completed by the early 2030s, while the K Line extension to Torrance could be done later that decade. The northern extension to the Hollywood Bowl won’t break ground until at least 2041.


    For more stories like this, follow Rail and Runway on Instagram and Facebook.

    LA Metro Los Angeles Trains
    Share. Facebook Twitter LinkedIn Threads Copy Link Email
    Travis Schlepp
    • Facebook
    • X (Twitter)
    • Instagram
    • LinkedIn

    Travis has been covering local and national news for more than a decade with bylines at some of the most prominent news organizations in the country. He’s covered a range of topics including travel, transit and sports, in addition to daily breaking news coverage. Travis is a Golden Mike nominated reporter, a two-time Southern California Emmy Award recipient and a second-place Spot News Coverage Award winner by the Associated Press as a member of the KEYT News Channel 3 team in Santa Barbara. Travis’ previous stories can be found on KTLA.com, The Hill, Yahoo News, MSN, and local news sites including KTVQ in Billings, Montana, and KEYT News Channel 3 in Santa Barbara. Previously, Travis served as the managing editor and operations lead at Dodgers Nation and LA Sports Report. Travis is also the editor-in-chief at DodgersDynasty.com.

    Related Posts

    Rendering of an Amtrak Airo trainset traveling among green vegetation. (Amtrak)

    Amtrak orders longer Airo trains for busy Northeast Corridor

    Rendering shows the proposed California High-Speed Rail bullet train traversing through the California Central Valley. (California High-Speed Rail Authority)

    California High-Speed Rail consultants return $1 million spent on restaurants, travel

    Rendering of an Ottawa gondola cabin travelling above the forest along the Gatineau Park corridor

    Ottawa gondola plan would connect downtown to local ski slope

    GTA VI screenshot from Grand Theft Auto VI courtesy of Rockstar Games

    Gamers get first look at ‘Grand Theft Auto VI’ and its full transit network

    Add A Comment
    Leave A Reply Cancel Reply

    Read more
    A subway train at the platform of the new D Line station at Wilshire and La Cienega show in this undated promotional image from LA Metro.

    LA Metro subway extension pushed back to fall 2027

    By Travis SchleppNovember 23, 2026 at 7:27 pm
    Rendering of an Amtrak Airo trainset traveling among green vegetation. (Amtrak)

    Amtrak orders longer Airo trains for busy Northeast Corridor

    By Travis SchleppNovember 23, 2026
    Rendering shows the proposed California High-Speed Rail bullet train traversing through the California Central Valley. (California High-Speed Rail Authority)

    California High-Speed Rail consultants return $1 million spent on restaurants, travel

    By Travis SchleppNovember 20, 2026
    Sponsored - Viator
    Follow Rail and Runway
    • Facebook
    • Instagram
    • Twitter
    • Threads
    • LinkedIn
    • YouTube
    • Bluesky

    Subscribe to Updates

    Get Rail and Runway delivered right to your inbox. Subscribe to our newsletter!

    About Us
    About Us

    Rail and Runway covers the way we move, and where we go: from transit and travel to culture and entertainment, and how to make the most of it.

    Facebook X (Twitter) Instagram YouTube Bluesky LinkedIn Threads
    Latest
    A subway train at the platform of the new D Line station at Wilshire and La Cienega show in this undated promotional image from LA Metro.

    LA Metro subway extension pushed back to fall 2027

    November 23, 2026 at 7:27 pm
    Rendering of an Amtrak Airo trainset traveling among green vegetation. (Amtrak)

    Amtrak orders longer Airo trains for busy Northeast Corridor

    November 23, 2026
    Rendering shows the proposed California High-Speed Rail bullet train traversing through the California Central Valley. (California High-Speed Rail Authority)

    California High-Speed Rail consultants return $1 million spent on restaurants, travel

    November 20, 2026
    Sponsored - Viator
    • About
    • Contact
    • Privacy Policy
    • DodgersDynasty.com
    © 2026 Rail and Runway

    Type above and press Enter to search. Press Esc to cancel.